Bureaucracy hampers investments

Renewable Energy Projects on Hold Although by the end of 2024, Croatia has an obligation, according to the National Recovery and Resilience Plan, to build...

We reviewed HEP’s ten-year plan: We extracted the most important information, from connection deadlines, and meter replacements, to strategy.

The holder of investments in transmission lines, substations, and other network infrastructure is HEP-ODS (Croatian Electricity Distribution System Operator) For the refurbishment of existing and...

About 1300 MW of power plants are stalled because the State cannot make one decision for a year and a half

The law obligates investors to obtain all necessary permits within seven or five years, a requirement they may now "miss" There is enough electricity to...

Blocked Renewable Energy Projects in Croatia

Deadlines for the construction of renewable energy (RE) plants are expiring because all the necessary permits cannot be delivered on time. The entire system...

Croatia was fully powered by renewable energy sources for 4 days in December 2023 – RESC Report on Power Sector Trends for December 2023.

In December 2023, renewable sources achieved a share of 19.5% of the available electricity. The construction of solar power plants marked the development of new...

Conference on the Potential of Agrivoltaic Power Plants in Osijek

The Renewable Energy Sources of Croatia, in collaboration with the Faculty of Agrobiotechnical Sciences in Osijek, are organizing a conference in February 2024 on...

Hive Energy Ltd – new RES Croatia member

Hive Energy was founded in 2010 by Giles Redpath to participate in the significant solar PV expansion in the UK. Hive now operates from...

RES Simplify for the simpler and faster development of RES

With its REPowerEU plan, the European Union decided to increase investments in renewable energy sources and most of the clean renewable energy is expected...

REPowerEU is the new energy reality

The REPowerEU strategy and impact of electrification on energy independence is the title of the presentation given by Ivan Komušanac, adviser for electrification in...

Conditions for stepping up the energy transition

Due to the crisis and Russian energy supply, the European Union adopted ambitious plans and proclaimed that the production of energy from its own...

Popular articles

RES DAYS – open registrations

We are inviting you to the conference DAYS OF...

Renewable Energy Surpasses Fossil Fuels

RESC Report on Power Sector Trends for February 2024 Aware...

All Quiet at the Distribution Network Front

The proposed Ten-Year Development Plan for the HEP ODS...

Bureaucracy hampers investments

Renewable Energy Projects on Hold Although by the end of...

Sign up for our Newsletter

By using this form, you agree to Google reCAPTCHA, confirm that you are familiar with the RESC Privacy Policy and consent to the collection and processing of personal data.

Sponsored by