The wind farm Podveležje produces the first kilowatts of electricity

The wind aggregates at locations 7 and 8 of the Podveležje wind farm produced during the testing phase the first kilowatts of electricity delivered to the connection grid as posted by the portal Energetika-net.

The wind farm Podveležje with a capacity of 48 MW is located 10 kilometers east of Mostar and will have a total of 15 wind aggregates with an estimated production of approximately 130 GW annually.  The contractors are the consortium Siemens Gamesa Renewable Energy Croatia and Wind Power A/S from Denmark,

The value of the investment is about 83 million EUR and the construction is financed through a loan from the German Development Bank, KfW, and from funds of the Electrical Power Industry of Bosnia and Hercegovina (EPBiH).

The wind farm Podveležje is located 10 kilometres from Mostar with a total of 15 wind aggregates

Latest posts

Hive Energy Ltd – new RES Croatia member

Hive Energy was founded in 2010 by Giles Redpath...

MEPs back boost for renewables use and energy savings

The Industry, Research and Energy Committee wants to accelerate...

RES Simplify for the simpler and faster development of RES

With its REPowerEU plan, the European Union decided to...

The Council of the EU agrees with the higher goals for RES and energy efficiency

The Council yesterday adopted its negotiating positions (general approaches)...

REPowerEU is the new energy reality

The REPowerEU strategy and impact of electrification on energy...

Sign up for our Newsletter

Sponsored by