Tag: res

RES DAYS – open registrations

We are inviting you to the conference DAYS OF RENEWABLE ENERGY SOURCES (Dani OIE 2024), which will be held from June 12 to 14,...

Bureaucracy hampers investments

Renewable Energy Projects on Hold Although by the end of 2024, Croatia has an obligation, according to the National Recovery and Resilience Plan, to build...

With the installed 1300MW that are blocked, the share of renewable energy sources in electricity production would be 10% higher

Tea Dabić, a legal expert from RESC, was a guest in the "Financial Minute" segment of Studio4 on HRT, hosted by editor and presenter...

About 1300 MW of power plants are stalled because the State cannot make one decision for a year and a half

The law obligates investors to obtain all necessary permits within seven or five years, a requirement they may now "miss" There is enough electricity to...

Blocked Renewable Energy Projects in Croatia

Deadlines for the construction of renewable energy (RE) plants are expiring because all the necessary permits cannot be delivered on time. The entire system...

Croatia was fully powered by renewable energy sources for 4 days in December 2023 – RESC Report on Power Sector Trends for December 2023.

In December 2023, renewable sources achieved a share of 19.5% of the available electricity. The construction of solar power plants marked the development of new...